Cladding funding for buildings under 11 metres, and the window that opens in August

New Cladding Safety Scheme funding opens to residential buildings under 11 metres in England on 17 August 2026, and closes eight weeks later. The assessment that qualifies a building has to exist before you apply, and within the highest risk group the queue is ordered by the date and time the application arrives.

The SAMRISK Team 5 min read

For most of the past decade the remediation programmes drew a line at 11 metres, and attention followed the line. The buildings below it were not a different problem. They were a smaller one, unfunded, and usually held by owners without a route to the money.

That changes next month.

What has been announced

On 9 July 2026 the government confirmed new funding for residential buildings under 11 metres in England, delivered through the Cladding Safety Scheme. Applications open on 17 August 2026 and the window runs for eight weeks (GOV.UK, "Buildings under 11 metres: fund overview", 2026).

The fund is aimed at life safety fire risks from cladding and external wall systems on multi-occupied residential buildings. Two conditions define the estate it covers. The building has to be under 11 metres, and it has to contain two or more dwellings. Tenure does not decide it. Privately owned blocks and social housing are both in scope.

One exclusion is worth reading before anything else. Works that started before 9 July 2026 do not qualify. If a scheme is already on site, the funding is not retrospective.

The assessment is the gate

A building qualifies on the strength of a Fire Risk Appraisal of External Walls carried out in line with PAS 9980:2022, supported by the fire risk assessment where one exists. Unsafe cladding, for the purposes of the fund, means an external wall system where a risk to life from fire spread has been identified and is not tolerable without mitigation.

That definition does a lot of work. A concern about a material is not the test. Neither is an insurer asking questions, or a lender declining a flat. What the fund responds to is a competent appraisal, on the current methodology, that reaches a stated conclusion about life safety.

Blocks of this size are the ones least likely to have that document already. Under 11 metres there has been no registration duty, no gateway, and in many cases no reason anyone was prepared to pay for a full external wall appraisal. So for a good number of buildings the first task is not the application. It is commissioning the appraisal, and finding an assessor with capacity in a market where several thousand owners are about to want the same thing in the same six weeks.

Who is allowed to apply

Applications come from the responsible entity for the building, or an authorised representative acting for it. Leaseholders and residents cannot apply directly. They can tell Homes England about a building through the Tell us Tool, which is useful where a freeholder is absent or unresponsive, but it is not an application and it does not hold a place.

For a managing agent that means establishing, now rather than in the third week of August, which entity is the responsible one for each block. On small low-rise stock the answer is often less tidy than it looks. A right to manage company, a resident management company, an absent freeholder and an agent with a limited instruction can all sit around the same building.

Why the date and time matter

Applications are prioritised by cladding fire safety risk, and buildings assessed as high risk are taken forward first. Within that group, valid applications are progressed in the order they are received, and the date and time of submission set the position in the pipeline.

So there are two filters, not one. The appraisal decides which group a building lands in. The clock decides where it sits inside that group. An eight-week window with a queue behind it rewards the owner who had the paperwork finished in July.

What to have ready before 17 August

Four things, and each one is either in your records or it is not.

Which of your buildings are under 11 metres, measured and evidenced rather than assumed. The threshold is a measurement to the finished floor level of the top storey, and on a three storey block with a roof terrace or a sloping site the answer is not obvious from the outside.

Whether a PAS 9980 appraisal exists for each of them, when it was done, and whether its conclusion is still the current one after any works or any change to the guidance.

Who the responsible entity is for each block, with the evidence that supports it, and who is authorised to submit on its behalf.

What the external wall on each building is actually made of. Not the specification from the sales brochure, but what the survey found, with the photographs and the reports attached to it.

If assembling that list for a portfolio of low-rise blocks would take longer than the eight-week window itself, that is the finding, and it is worth acting on before the seventeenth.

Where the record lives

A funding window is a deadline with a document behind it, which makes it the same shape as every other compliance duty.

In SAMRISK the external wall build-up and what the survey found sits in materials against the building, so the answer to what the cladding is comes from the record rather than from a phone call. The appraisal and the fire risk assessment are versioned files in documents, which is what makes the current one identifiable. The risk itself lives in fire safety and in the building's risk assessments, with the height, the storey count and the tenure held once on the building rather than retyped into each new form. The application deadline and the assessor's site visit are dated items on the compliance calendar, and any remediation that follows becomes maintenance work with an owner and a completion date.

The fund will not reach every building that needs it, and eight weeks is not long. What it does reward is knowing, on the day the window opens, exactly which of your buildings are in scope and where their paperwork is.

Sources: GOV.UK, "Buildings under 11 metres: new funding" and "Buildings under 11 metres: fund overview", July 2026; PAS 9980:2022, Fire risk appraisal of external wall construction and cladding of existing blocks of flats.